Ufs notice register
* 20004 (T) |
Chart: 9312, 9313 |
Sweden. Kattegat. Göteborg. Bridge Älvsborgsbron. Works. Vertical clearance. |
|
|
Time: April 13 - until further notice Works on the Älvsborgsbron bridge in Göteborg. Vertical clearance is affected. A scaffolding is built under the bridge during the work. This reduces the vertical clearance to 43 meters where the scaffold is. The vertical clearance is otherwise unchanged. The scaffolding is built in stages under parts of the bridge. Suitable passage in the fairway will vary during the period. Mariners are urged to pay close attention to the restrictions below. The restrictions have been set due to safety and health risks for personnel working on the scaffold. Contact: VTS Gothenburg VHF channel 13. Scaffolding contractor tel: +46 (0)703- 05 92 35. |
| Vessels | Restrictions | Information |
|---|---|---|
| Air draft less than 35 meters | No restrictions under the bridge | Vessels can pass under scaffolding |
| Air draft 35 - 40 meters | Vessels are urged to pass under the part of the bridge that has no scaffolding | Safety and health reasons for personnel |
| Air draft 40 - 42 meters | Vessels shall pass under the part of the bridge that has no scaffolding | Safety and health reasons for personnel |
| Air draft over 42 meters | Vessels MUST pass under the part of the bridge that has no scaffolding | Contact VTS Gothenburg 20 min before passing under the bridge. Scaffolding will be evacuated |
|
|
| Bridge Älvsborgsbron in Göteborg | a) | 57-41,47N | 011-54,08E |
Bsp Västkusten S 2025/s47, s58 |